For each development a development work flow plan can be set up to monitor progress. Track the project from concept through to completion. The plan is visible in the Development Summary view.
- Click [Expand] to open the Work Flow Plan tab.
- Using the calendars add the estimated start and/or estimated finish dates.
- As the project is progressed through each stage use the calendars to add the actual start and finish dates
- Click [Save] to save your work and click [Expand] to close the tab.